Tillsonburg inlet trunk sanitary sewer replacement

2026-08-12 · FS2026-17 Attachment 2

2026-08-12 · FS2026-17 Attachment 2

Tillsonburg inlet trunk sanitary sewer replacement

Contract Award – <10% over budget

$1,537,648 · Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total

Consequence: Tillsonburg inlet trunk sanitary sewer replacement

Open the source record
  1. FS2026-17 Attachment 2: Summary of In-Year Budget Approvals
    Source date
    2026-08-12
    Date context
    Report dated August 12, 2026; publication and individual approval dates not established
    Event / reporting date
    2026-08-12
    Reviewed
    2026-10-30
    Retrieved
    2026-10-30
    Evidence status
    verified_primary
    Evidence note
    15 specified rows inspected. Amount is reported in-year approval, not actual spending, bidder price or vendor invoice. Individual approval dates and tax treatment are unspecified.

The amount in this decision

$1,537,648

Reported in-year budget approval to award funds; not actual expenditure, bid amount, or vendor-invoice total

2026-08-12 · Contract Award – <10% over budget

Authority & recorded votes

County published in-year approval summary

Individual votes are not confirmed.

Connected projects

County · Water, drainage & wastewater

Tillsonburg inlet trunk sewer replacement

Replace the sewer near Old Vienna Road with manholes, connections, restoration and erosion protection. Construction is scheduled for October 19 to mid-December 2026. Dates remain subject to change; actual commencement and completion have not been independently confirmed.

Tillsonburg

Awardee named; construction scheduled October 19–mid-December 2026; actual start unconfirmed
2026 allocation
$1,350,000
Named supplier
Birnam Excavating Ltd.
Next target
2026-12 · Expected completion: mid-December 2026
Latest update
2026-10-16 · Revised schedule and pedestrian access announced
Who’s actually in charge?

Who’s actually in charge?

01

Tillsonburg council

Municipal services, local roads, recreation, zoning and the local budget.

Explore this level →
02

Oxford County

County roads, water and wastewater, housing services, paramedics and County planning.

Explore this level →

Meet your representatives