Tillsonburg project
On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Tillsonburg
Responsible authority Tillsonburg Current stage Open to the publicAs of 2026-07-02 Stage and project evidence: [1] [2] [3] [4] [5]
Original whole-project baseline established separately $4,690,000
Next target No next date listed The replacement Kinsmen pedestrian bridge and adjoining Veterans Memorial Walkway reopened July 2, 2026.
Remove old deck, partly remove piers, install prefabricated pedestrian bridge and restore trail.
Project 181
Who approves and delivers this project? Municipal authority
Town of Tillsonburg Budget and municipal project owner; contractor/individual decisions require separate records.
Sources for this record: [1]
Construction contractor
Lancoa Contracting Inc. Retained by Town; March delay notice assigns schedule-related extra costs to contractor/supplier.
Sources for this record: [3] [4]
Engineering contract administration recommendation
Planmac Engineering Inc. Staff report allowance $166,327 including net HST; separate executed agreement not extracted.
Sources for this record: [2]
Bridge supplier
Algonquin Bridge Designed and supplied the replacement steel bridge and support piers.
Sources for this record: [5]
Money Project money Budget and forecast Original whole-project baseline established separately $4,690,000 Other financial measures Prior approved carryforward envelope $4,690,000 Original whole-project baseline established separately Latest spending total not published here.
CAD · See individual funding/contract source · Prior approved carryforward envelope; not current remaining balance Project money evidence: [1] [2] [3] [4] [5]
Where the funding comes from $4,690,000 Listed funding total
Reserves Published carryforward funding envelope; miscellaneous is not identified as secured grant income. $1,628,90034.7% of listed total Development charges Published carryforward funding envelope; miscellaneous is not identified as secured grant income. $1,004,80021.4% of listed total Debentures Published carryforward funding envelope; miscellaneous is not identified as secured grant income. $2,056,30043.8% of listed total Listed funding adds to the original budget amount. CAD. Timeline 2025-07-16 award Contractor named Town confirms Lancoa retained; actual award date not provided.
Sources for this record: [3]
2025-08-05 Target date passed; milestone status needs a verified update Mobilization planned Resident notice target.
Sources for this record: [3]
2026-03-30 Target date passed; milestone status needs a verified update Completion target revised March notice moves mid-March construction target to first week of May, weather-dependent restoration separately.
Sources for this record: [4]
2026-07-02 completion Bridge and walkway reopened Opening confirmed in the bridge supplier’s July 10 project account.
Sources for this record: [5]
Contracts RFT2025-005 · Contractor engagement verified; award amount recommendation
Lancoa Contracting Inc.
Published bid $2,742,142.80
Published award / contract value Not established
Unit price Not established The published bid does not establish the final executed contract value. Bid excludes HST. Staff recommended construction amount $2,790,405 includes non-refundable HST.
Do not map the recommended $2,790,405 to awardAmount without the adoption/award resolution; contractor retention is verified by Town construction notice.
Sources for this record: [2] [3]
Open procurement record Decisions No separate decision record is linked. Approval details may appear in the timeline or source documents.
Outcomes Pedestrian connection between west-side neighbourhoods and downtown restored.
Questions What were the certified final bridge and walkway costs, including changes? Scope & interpretation notes No savings claimed: full final costs and the approved revised appropriation are not available in opened records. Report’s alternative material offer is not treated as selected. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: tillsonburg-budget-page-308
Publisher Town of Tillsonburg
Published 2026-01-07
Event / reporting date 2026-01-07
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status Published budget binder; adoption source paired
Passage / page PDF page 308 Open in source library
Source ID: tillsonburg-kinsmen-tender-report
Publisher Town of Tillsonburg
Published 2025-06-16
Event / reporting date 2025-06-16
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status staff recommendation; contractor engagement separately confirmed
Passage / page PDF pp.1–6; tender table and financial impact
Evidence notes Recommends construction $2,790,405 net non-refundable HST plus Planmac $166,327 plus contingency $295,673. $3,252,404 total is a recommended forecast, not verified final expenditure or council-approved revised appropriation. Open in source library
Source ID: tillsonburg-kinsmen-construction
Publisher Town of Tillsonburg
Published 2025-07-16
Event / reporting date 2025-07-16
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Passage / page PDF pp.1–2
Evidence notes Names Lancoa Contracting Inc. as retained contractor. Closure window August 5–December 18, 2025 is not a final completion certificate. Open in source library
Source ID: tillsonburg-kinsmen-delay
Publisher Town of Tillsonburg
Published 2026-03-30
Event / reporting date 2026-03-30
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Passage / page Updated schedule and cost responsibility paragraphs
Evidence notes Mid-March target revised to first week May 2026 due to structural supplier production. Additional crane/remobilization costs assigned to contractor and supplier. Does not establish project completion. Open in source library
Source ID: tillsonburg-kinsmen-opened-2026
Publisher Algonquin Bridge
Published 2026-07-10
Event / reporting date 2026-07-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published
Passage / page Opening paragraph; reconstruction description; Project at a glance
Evidence notes First-party bridge supplier account. Owner Town of Tillsonburg, contractor Lancoa and consultant Planmac identified. Supplier narrative about savings is not a final municipal cost certificate. Open in source library