On this page Overview Money Timeline Contracts Decisions Outcomes Questions Evidence At a glance
Location Tillsonburg
Responsible authority Oxford County Current stage December 2026 construction target; completion unverifiedAs of 2026-10-29 Stage and project evidence: [1] [2] [3] [4]
2026 allocation $5,590,667
Next target 2026-12 · Expected completion Build onsite treatment at 445 Broadway Street, demolish the existing facility at 451 Broadway Street and upgrade services.
Treatment facility and site services at 445 and 451 Broadway Street.
Project 960200
What happens next 2026-12 · Expected completion
County says existing drinking water remains safe; the project adds arsenic filtration so this well can supply water independently in future.
Sources for this record: [2]
Who approves and delivers this project? Expenditure approval
Oxford County Council County capital budget authority; individual votes not inferred.
Sources for this record: [1]
Asset owner and delivery lead
Oxford County Public Works County project located within the local municipality; local council is not the County contract manager.
Sources for this record: [5]
Money Project money Annual allocation 2026 allocation $5,590,667 2026 expenditure allocation including carryforward Latest spending total not published here.
CAD · Project allocation as published; bid HST basis not established · 2026 expenditure allocation including carryforward Project money evidence: [1] [2] [3] [4]
Where the funding comes from $5,590,667 Listed funding total
$3,605,71964.5% of listed total $901,31116.1% of listed total Grants Dedicated 2026 capital account. See the budget row for financing timing. $1,083,63719.4% of listed total Listed funding adds to the 2026 allocation amount. CAD. Timeline 2025-11 Target date passed; milestone status needs a verified update Tentative construction start Early November 2025.
Sources for this record: [2]
2026-12 original target Expected completion County says existing drinking water remains safe; the project adds arsenic filtration so this well can supply water independently in future.
Sources for this record: [2]
Contracts TENDER-ENG-2025-637 · awardee named in annual register
Baseline Constructors Inc.
Published bid $6,522,360
Published award / contract value Not established
Unit price Not established The published bid does not establish the final executed contract value. Not established in annual register
2025 award connected to current 2026 work. The annual register names the awardee but leaves the contract value and award date unpublished.
Sources for this record: [3]
Open procurement record Decisions 2025-12-10 · Oxford County Council
County approval confirmed by the official budget hub; the detailed approved document is the financial source.
$406,890,915 · Detailed document total of operating plus financed capital; the budget hub headline conflicts.
Consequence: General levy: $96,680,548; library levy: $6,297,357; court security levy: $61,266. Water and wastewater are supported by utility rates.
Sources for this record: [6] [7]
Outcomes Completion not confirmed.
Questions What is the current approved project total, including carryforward and changes? What spending and final completion or acceptance records are available? Scope & interpretation notes The 2026 allocation is $678,154 carryforward plus $4,912,513 new funding. Funding comprises $3,605,719 rates/reserves, $901,311 development charges and $1,083,637 grants. This is not the total historic project cost. Sources & evidence These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.
Source ID: county-budget2026-p46
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 46; printed page 46
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-construction
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official project notice
Passage / page Named project sections; updates through September 2026 Open in source library
Source ID: county-award-tender-eng-2025-637
Publisher Oxford County
Reporting period 2025 award register; 2026 active project
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status published record
Passage / page TENDER-ENG-2025-637; named awardee and bidder-price row
Evidence notes Prior-year award linked to a project active during 2026. The contract value cell is --; the bid is not a signed contract value. Open in source library
Source ID: county-construction-20261029
Publisher Oxford County
Reporting period 2026
Reviewed 2026-10-29
Retrieved 2026-10-29
Verified 2026-10-29
Evidence status verified_primary
Decision / approval status official source
Passage / page Named road, bridge, culvert and water/wastewater project sections
Evidence notes Current central-page text was reviewed. Named completion notices apply only to their stated scope; a passed target is not proof of completion. Newer linked PDF handouts were not all independently read. Open in source library
Source ID: county-budget2026-p5
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 5; printed page 5
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Source ID: county-budget-hub
Publisher Oxford County
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status official approval summary
Passage / page 2026 approved budget section
Evidence notes The hub reports $406.1 million total and $278.2 million operating, while the approved detailed PDF reports $406,890,915 and $279,035,275. Open in source library
Source ID: county-budget2026-p58
Publisher Oxford County
Published 2026-01-14
Event / reporting date 2025-12-10
Reporting period 2026
Retrieved 2026-10-01
Verified 2026-10-01
Evidence status verified_primary
Decision / approval status approved
Passage / page PDF page 58; printed page 58
Evidence notes File date is January 14, 2026; County hub identifies December 10, 2025 Council approval. Detailed source governs figures; hub headline differs. Open in source library
Copy this view Print