02Follow the moneyTillsonburg

Tillsonburg · Procurement record

Asphalt replacement – Hardy Avenue

RFT2026-005

Money & projects Explore sections
Tillsonburg procurementClosed; award not verified

Supplier

Not established in the reviewed record

Procurement method
RFT
Award date
Not established
Contract term
Not established

From bid to payment

Closed; award not verified

  1. Published bidAmount not published
  2. RecommendationAmount not published
  3. Award / contractAmount not published
  4. Recorded paymentsAmount not publishedNo payment amounts attached
Not stated in opened record · Bid, award and payment are separate measures.

Full-depth asphalt work. Procurement price/value not published in opened record; 2026 asphalt program allocation is a separate budget basis.

Contract changes & payments

Contract changes unconfirmed.

Payments not confirmed.

Related project

Tillsonburg · Roads & bridges

Asphalt maintenance

Asphalt maintenance

Tillsonburg

Budgeted · delivery unconfirmed
2026 allocation
$240,000
Next target
No next date listed

What still needs an answer

Sources & evidence

These records support the linked project or financial entries. A record link does not establish that every amount or outcome appears in every source. Dated observations and earlier qualifications remain separate.

  1. Asphalt replacement – Hardy Avenue procurement record

    Source ID: tillsonburg-tender-asphalt

    Publisher
    Town of Tillsonburg
    Retrieved
    2026-10-01
    Verified
    2026-10-01
    Evidence status
    verified_primary
    Passage / page
    Bid summary, status, award summary and public results
    Evidence notes
    Full-depth asphalt work. Procurement price/value not published in opened record; 2026 asphalt program allocation is a separate budget basis.

    Open in source library

Make sense of the money

Make sense of the money

Your taxes called. They’d like a receipt.

Budget
Planned costs for a stated year or project.
Annual allocation
Funding assigned for one year. It may be part of a larger project.
Lifetime project budget
The stated budget for the full project across its years.
Forecast
An estimate of the eventual cost, as of the date shown.
Tax requirement (levy)
The amount to raise from property taxes, after other funding.
Contract award
The accepted contract price, with its stated tax and scope.
Recorded costs or payments
Amounts reported for the period shown. They do not establish project completion.

County spending and County taxes explained →

Open the full money explanation